Large Bushing Guard Installation Guide

DE-ENERGIZED INSTALLATION NOTES

1.

Align one side of the Reliaguard Bushing Guard under the bushing’s uppermost shed. If installing Reliaguard GreyEEL® conductor guard onto conductor. refer to the GreyEEL® installation guide prior to alignment.

2.

Close the Bushing Guard so that the two circular hinge latches (indicated with red arrows) fit into the opposite half’s circular receptacles.

3.

Ensure guard is closed by firmly pressing body halves. This will engage square snaps into their receptacles.

4.

Thru-holes are provided for the optional use of push pins or zip ties as a secondary closure. These are not required for retention and are provided only for convenience of users who prefer a secondary closure method.

DE-ENERGIZED REMOVAL NOTES

Remove Bushing Guard by clipping the zip ties or heads off the black pins with suitable cutter. Then pressing in both loop latch snaps. Separate guard to remove.