Universal Regulator Kit Install Instructions

FIRST INSTALL

REGULATOR GUARD – ARRESTER PORTION

DE-ENERGIZED INSTALLATION NOTES

1.

Identify each arrester bracket guard as either left or right. Ensure the hinged side is up.

2.

Dry fit each guard on the arresters. Fingers should fit over first skirt of insulator, if not trim to fit.

3.

To trim guards to length, measure the following: Left : [A] to [B], edge of NEMA to first insulator skirt. Right: [C] to [D], edge of NEMA to first insulator skirt.

4.

Measure and mark trim lines for each guard. Trim with snips or shears.

5.

Dry fit guards once again to ensure proper fit. Guards should fully enclose energized portions of arrester and first skirt on each end, leaving only the center of insulator visible • Install push fasteners. Installation is complete.

Note that push fasteners are one-time-use and must be cut to be removed. Side cutters work best to remove.

SECOND INSTALL

REGULATOR GUARD – ARRESTER PORTION

DE-ENERGIZED INSTALLATION NOTES

1.

Install Conductor Cover if using.

If using conductor cover, ensure it is installed all the way down to wire connector.

2.

Align guard under top skirt of bushing, over previously-installed arrester guard.

3.

Dry fit bushing guard to ensure proper fit. Guard should enclose the top insulator skirt and align to arrester. Do not cover more than the top skirt.

4.

Mark and drill (1/4” hole) into arrestor at 2 existing bushing-section guard holes. These will secure bushing-section of guard to the arrester section.

5.

Install push pins in all 6 guard holes. Installation is complete.